Windy Plains
Renewable Energy Park

The proposed Windy Plains Renewable Energy Park (REP) is expected to have an installed capacity of nominally 1,400 MW from wind turbines, complemented by battery storage.

It is planned to operate for approximately 30 years, after which the turbines and associated infrastructure could be removed and the land reinstated or upgraded with new equipment.

Key Components

Wind Turbines

Approximately 197 wind turbines, each with a generating capacity of around ~7 MW.

Site Tracks

Internal access tracks connecting turbines, substations, and operations facilities.

Grid Connection Infrastructure

One or more on-site substations will collect power generated from the turbines and export it to the planned CopperString 330 kV transmission line via a switch station.

Monitoring Masts

Temporary and permanent masts to measure wind speed and direction, which help calculate energy production levels.

Site Access

Potential site access via Ardbrin Road or Proa Road, with connections to the Flinders Highway near Julia Creek or Nelia.

Construction Facilities

Temporary construction compounds, laydown areas, wash-down facilities, and worker accommodation, as needed, during the build phase.

Project Status and Timeline

Latest Update
10th July, 2025

Windy Plains REP has recently completed the Project Feasibility stage and is now at the very beginning of the Assessment, Consultation, and Design phase. This next stage involves more detailed environmental, planning, and technical assessments – including field surveys – to better understand the site and surrounding area.

Community and stakeholder consultation will also begin, helping to shape the project design and guide the development of a Community Benefit Agreement. There will be multiple opportunities for public input throughout this phase, including community open days and other engagement activities.

Future Assessments & Approvals

As the project progresses, detailed field surveys and community consultation will inform the design. Approvals from both the Queensland Government and Commonwealth regulators (e.g. EPBC referral) will be pursued.

Future Construction

Should the project proceed following the feasibility and approvals processes, construction is anticipated to take around two years.

Project Stages

Below is a general overview of the stages a wind energy project typically goes through:

Project Feasibility

Initial investigations to assess whether the site could be suitable for a wind farm (e.g. wind resource, land use, environmental constraints).

Assessments, Consultation & Design

Environmental, planning, and technical assessments (including field surveys).

Stakeholder and community consultation to inform project design and Community Benefit Agreement.

Opportunities for public input, such as open days.

Development Approvals

Social Impact Assessment and Community Benefit Agreement.

Submission of applications to State (Queensland Government) and Commonwealth (EPBC referral) agencies.

Approvals or conditions may be issued to consent to project construction and operation.

Pre-Construction

Obtain remaining permits (e.g. road access, local council approvals).

Finalise detailed design, engineering, and procurement for construction.

Construction & Operation

Construction typically spans about two years.

Community engagement continues throughout construction and operations.

Once operational, the site contributes significant clean energy to the grid.